Name
Capella University
PM-FPX 4060 Risk Management in Project Management
Prof. Name
Date
The Guided Customer Service Program (GCSP) is a planned platform replacement initiative for Webster Insurance designed to modernize its customer service database, reduce call-handling delays, support membership growth, and meet Centers for Medicare & Medicaid Services (CMS) and Health Insurance Portability and Accountability Act (HIPAA) compliance requirements within an approved $2,000,000 budget and an original schedule spanning June 1, 2021, to May 31, 2023.
Led by project manager Angela Guthrie and sponsored by Steve Smith, the program relies on a structured work breakdown structure (WBS), phased deployment, risk governance, and formal change control to replace legacy infrastructure without disrupting daily service operations.
The project charter defines the purpose, governance boundaries, schedule baseline, and financial structure for GCSP. It aligns stakeholders on expected business outcomes and establishes rules for evaluating scope and cost adjustments.
| Project Element | Plan Details |
| Project Title | Guided Customer Service Program (GCSP) |
| Organization | Webster Insurance |
| Project Sponsor | Steve Smith |
| Project Manager | Angela Guthrie |
| Original Start Date | June 1, 2021 |
| Original Completion Date | May 31, 2023 |
| Approved Budget | $2,000,000 |
| Overrun Threshold | 4% ($80,000, or $2,080,000 mathematical cap) |
| Core Execution Strategy | Phased design, migration, integration, testing, deployment, and acceptance |
The dates listed in the charter represent original baseline targets rather than a statement of current project status.
Webster Insurance allocated $2,000,000 to GCSP, with a 4% overrun limit ($80,000) identified as a project success constraint. Reaching the $2,080,000 ceiling does not grant automatic spending authority; any cost change must go through formal organizational change control and executive approval.
| Budget Category | Allocated Amount |
| Project Management and Oversight | $150,000 |
| System Design and Architecture | $600,000 |
| Software Installation and Migration | $150,000 |
| Migration of Systems into the New Program | $100,000 |
| Other Project Costs and Remaining Budget | $1,000,000 |
| Total Approved Budget | $2,000,000 |
Because $1,000,000 remains unitemized in the initial breakdown, the team should assign those funds to explicit categories such as licensing, integration labor, quality assurance testing, training, infrastructure, and contingency reserves prior to financial sign-off.
GCSP replaces an aging customer service database that has experienced crashes, service bottlenecks, and member dissatisfaction as Webster Insurance grows. Success depends on tying each objective to documented, measurable acceptance criteria.
The new customer service platform is intended to support growth and operational efficiency through several core outcomes:
Increase system availability and reliability for customer service teams.
Reduce average call-handling time, service delays, and operating costs.
Provide a clear, accessible agent interface while supporting growing membership.
Migrate required customer and operational records accurately from the legacy database.
Integrate the replacement platform with relevant existing systems.
Satisfy applicable CMS rules and HIPAA privacy and security obligations.
Complete testing, staff training, technical documentation, and formal sign-off before closure.
Tangible outputs across the project lifecycle must be assigned to clear owners, verified against acceptance criteria, and approved at key milestones:
Initiation Deliverables: Team rosters, the project management plan, initial meeting schedules, stakeholder roles, reporting rules, and documented assumptions.
Design and Delivery Deliverables: Integration specifications, meeting notes, progress reports, updated schedules, system demonstrations, and architectural or migration decision logs.
Final Delivery and Acceptance Package: Completed program database, system integrations, integration summary, applicable CMS compliance sign-off, financial closeout records, formal customer acceptance, and lessons learned.
Any skipped numbers in the original deliverable list should be standardized into a single approved register so items are not overlooked during sign-off.
Maintaining strict scope boundaries prevents unapproved expansion and protects cost and schedule baselines.
In Scope: Project management, system design, scheduling, software licensing and upgrades, data migration, system integration, quality assurance and user acceptance testing, deployment planning, maintenance arrangements, operational training, and a product package containing the Salesforce contract and PDF design presentation.
Out of Scope: Replacing unrelated systems, customer travel or lodging costs, unapproved design modifications without added funding, training on unrelated tools, and post-completion onboarding.
GCSP uses structured planning, cross-functional coordination, and phased rollout so customer service agents can continue assisting policyholders while the new system is built and introduced.
The team starts by validating business requirements and cataloging limitations in the current database. From there, specialists build the target architecture, configure the platform, plan data migration, and define integration interfaces.
Compliance reviews should happen continuously throughout execution rather than waiting until launch. Catching regulatory or security gaps early keeps remediation practical and cost-effective. Project progress is tracked against approved milestones, budget baselines, and acceptance criteria, with Angela Guthrie coordinating department leads, resolving day-to-day conflicts, and escalating issues beyond her authority.
| WBS ID | Activity | Original Start | Original Finish | Primary Deliverables |
| 1.0 | Project Initiation | June 1, 2021 | June 15, 2021 | Team roster and project management plan |
| 1.1 | System Design and Architecture | June 16, 2021 | August 30, 2021 | System design document and architecture plan |
| 1.2 | Software Installation and Migration | September 1, 2021 | November 30, 2021 | Installed software and migration report |
| 1.3 | System Integration and Testing | December 1, 2021 | February 28, 2022 | Integration report and testing results |
| 1.4 | Delivery and Acceptance | March 1, 2022 | May 31, 2023 | Final system and compliance sign-off |
| WBS ID | Task Description | Original Target Date |
| 1.1 | Verify customer needs and project requirements | June 1, 2021 |
| 1.3 | Confirm Salesforce as the selected software | June 15, 2021 |
| 1.2 | Create the project schedule | July 1, 2021 |
| 1.4 | Identify project stakeholders | July 1, 2021 |
| 2.1 | Develop the bid or request for proposal | July 5, 2021 |
| 2.2 | Release bid or request-for-proposal documents | July 10, 2021 |
| 2.3 | Review bid documents | July 11, 2021 |
| 2.4 | Finalize the vendor contract | July 17, 2021 |
| 3.1 | Develop the design responsibility matrix | August 15, 2021 |
| 3.2 | Complete the new system design | December 1, 2022 |
| 5.1 | Perform compliance testing | December 5, 2022 |
| 3.3 | Obtain design approval | December 5, 2022 |
| 3.4 | Prepare the final program release | January 1, 2023 |
| 4.1 | Begin usability testing | January 1, 2023 |
| 4.2 | Finalize program deployment | March 1, 2023 |
| 4.3 | Install the system and confirm access | April 1, 2023 |
| 5.2 | Provide customer training | May 15, 2023 |
| 5.3 | Obtain customer sign-off and document lessons learned | May 31, 2023 |
Several target dates and task sequences in the original plan conflict or appear out of order, such as listing compliance testing on December 5, 2022, before the final program release on January 1, 2023, and placing usability testing alongside or after release milestones. Using a scheduling tool such as Microsoft Project, the project manager should reconcile dependencies, milestones, and dates before locking the schedule baseline.
Clear accountability and predictable reporting keep departments aligned across design, integration, compliance, and customer support.
| Name | Role | Primary Responsibility | Project Involvement |
| Steve Smith | Project Sponsor | Provides sponsorship and approvals | All phases |
| Angela Guthrie | Project Manager | Coordinates scope, schedule, budget, risks, and delivery | All phases and tasks |
| Ingrid Sing | Product Manager | Ensures the solution meets customer needs | Design and engineering |
| Tracy Weave | Human Resources Manager | Addresses staffing and HR-related matters | All phases for HR activities |
| Gina Willis | Procurement Manager | Coordinates procurement and accounts payable/receivable tasks as assigned | All phases |
| Deb Keplin | Project Administrator | Tracks change orders and project documentation | All phases |
| Danny Senn | Integration Manager | Coordinates system integration | Program integration |
| Joyce Miller | Usability Manager | Oversees usability testing | Program integration |
| Beatrice Jones | Customer Representative | Serves as the customer liaison | Stakeholder coordination |
High-priority stakeholders require targeted cadence and participation:
Amy Johnson (Program Manager): High interest and high impact; needs regular status reports, milestone updates, and cross-departmental risk alerts.
Charles Davidson (Lead Developer): Medium interest and high impact; benefits from weekly development check-ins and technical feedback loops to surface integration blockers early.
Elizabeth Clark (Compliance Officer): High interest and medium impact; should participate in compliance reviews, requirement validation, and testing gates.
Michael Thompson (IT Support Lead): Medium interest and medium impact; coordinates infrastructure readiness, system access, troubleshooting, and post-launch support.
Contact details should be verified and stored in a secure project directory before distribution, and stakeholder influence levels should be updated whenever roles or decision rights shift.
Internal Updates: Weekly project meetings and email updates covering progress, upcoming work, open issues, dependencies, and corrective actions, with more frequent technical coordination during integration and testing.
External Leadership Updates: Biweekly client meetings and status reports with Webster Insurance management to share progress, gather feedback, review major deliverables, and flag escalation items.
Change Communications: Targeted notices issued whenever changes affect requirements, integrations, budgets, or deployment dates, explaining what is changing, why it is needed, how work is affected, and what stakeholders must do next.
Effective risk management for GCSP groups potential disruptions across technical, management, organizational, and resource categories using a risk breakdown structure (Hillson, 2002) and tracks them in a living risk register.
| Risk Area | Initial Assessment | Mitigation Strategy | Responsible Role |
| Scope Definition | Initially confirmed | Validate scope and duration with stakeholders | Project team |
| Requirements | Initially identified | Obtain approval for system requirements and integrations | Product manager |
| Estimates and Assumptions | Pending verification | Review supplier estimates and regulatory requirements | Procurement manager |
| Technical Processes | Initially considered adequate | Confirm infrastructure and licensing requirements | Procurement manager |
| Legacy System Compatibility | Requires verification | Test application programming interfaces and data feeds | Product manager |
| External System Dependencies | None identified initially | Reassess interfaces and dependencies during design | Integration manager |
| Design Alignment | Initially considered adequate | Validate architecture against requirements and constraints | Product and integration managers |
| System Performance | Initially expected to meet needs | Conduct performance and usability testing | Project team |
| Reliability and Maintenance | Requires verification | Perform ongoing functional and operational testing | Project manager and technical leads |
| Information Security | Compliance expected | Validate applicable security controls throughout implementation | Product manager and compliance officer |
| Testing and Acceptance | Testing planned | Establish test cases, defect thresholds, and acceptance criteria | QA and project managers |
| Team Responsibilities | Requires confirmation | Review the charter and obtain role acceptance | Project manager |
| Operational Disruption | Expected during integration | Schedule phased deployment and prepare fallback procedures | Project manager |
| Departmental Conflicts | Unresolved in the original plan | Establish decision rights and a conflict-resolution process | Project sponsor |
| Resource Availability | Initially considered adequate | Confirm capacity, skills, and workload throughout the project | Project team |
Entries originally marked as not applicable or undetermined should be actively reviewed rather than assumed closed. In particular, an initial note that system safety was not addressed warrants follow-up to confirm operational continuity, access controls, and safety safeguards.
Strengths: Experienced project staff, executive backing, a clear business need for modernized service software, ongoing organizational growth, and a structured project management framework.
Weaknesses: Need to maintain live customer service during a phased cutover, higher coordination demands while old and new processes overlap, lean specialist staffing, and estimates or records requiring verification.
Opportunities: Faster call handling, higher system reliability, better access to customer data, standardized workflows, stronger reporting, and future service improvements.
Threats: Integration errors, unexpected costs, compliance gaps, schedule slips, technical skill gaps, and potential member attrition if legacy issues persist before cutover.
Key constraints include the $2,000,000 budget baseline, limited single-person leadership in key roles (such as one product manager and one integration manager), busy service periods requiring phased rollout, and limited pre-deployment usability testing that must be strengthened so critical workflows are verified before launch.
Key assumptions include continued financial stability at Webster Insurance, expected performance from the selected Salesforce platform, detailed design drafts, regulatory alignment, scheduled meetings, customer sign-off, and timely financial closeout. Each assumption must be tested and verified with evidence rather than taken for granted.
Project success requires meeting agreed scope, approved requirements, accurate data migration, verified integration and usability testing, regulatory sign-off, budget discipline, and measurable post-launch operational gains, including validating the projected 18-month return on investment with actual cost and savings data.
The Guided Customer Service Program replaces Webster Insurance’s outdated customer service database with a scalable, compliant platform that reduces call-handling delays, supports membership growth, and meets CMS and HIPAA requirements with minimal operational disruption.
Angela Guthrie serves as project manager alongside project sponsor Steve Smith, operating under an approved budget of $2,000,000 and an original timeline from June 1, 2021, through May 31, 2023.
Customer service staff must continue handling member inquiries while the platform is configured, integrated, and tested, so a phased deployment limits service disruption, supports controlled testing, and allows fallback before full rollout.
The project manager should reconcile overlapping or out-of-sequence WBS dates (such as compliance testing relative to final release and usability testing), allocate the remaining $1,000,000 budget into defined categories, resolve departmental decision rights, and verify any items initially marked undetermined or unaddressed.
Centers for Medicare & Medicaid Services. (n.d.). Regulations and guidance. U.S. Department of Health and Human Services. https://www.cms.gov/regulations-and-guidance
Hillson, D. (2002). Extending the risk process to manage opportunities. International Journal of Project Management, 20(3), 235–240. https://doi.org/10.1016/S0263-7863(01)00074-6
U.S. Department of Health and Human Services. (n.d.). Health information privacy (HIPAA). https://www.hhs.gov/hipaa/index.html