PM FPX 4060 Assessment 3 Project GCSP

PM FPX 4060 Assessment 3 Project GCSP

Name

Capella University

PM-FPX 4060 Risk Management in Project Management

Prof. Name

Date

PM FPX 4060 Assessment 3 Project GCSP

The Guided Customer Service Program (GCSP) is a planned platform replacement initiative for Webster Insurance designed to modernize its customer service database, reduce call-handling delays, support membership growth, and meet Centers for Medicare & Medicaid Services (CMS) and Health Insurance Portability and Accountability Act (HIPAA) compliance requirements within an approved $2,000,000 budget and an original schedule spanning June 1, 2021, to May 31, 2023.

Led by project manager Angela Guthrie and sponsored by Steve Smith, the program relies on a structured work breakdown structure (WBS), phased deployment, risk governance, and formal change control to replace legacy infrastructure without disrupting daily service operations.

Project Charter and Budget Overview

The project charter defines the purpose, governance boundaries, schedule baseline, and financial structure for GCSP. It aligns stakeholders on expected business outcomes and establishes rules for evaluating scope and cost adjustments.

Core Charter Parameters

Project ElementPlan Details
Project TitleGuided Customer Service Program (GCSP)
OrganizationWebster Insurance
Project SponsorSteve Smith
Project ManagerAngela Guthrie
Original Start DateJune 1, 2021
Original Completion DateMay 31, 2023
Approved Budget$2,000,000
Overrun Threshold4% ($80,000, or $2,080,000 mathematical cap)
Core Execution StrategyPhased design, migration, integration, testing, deployment, and acceptance

The dates listed in the charter represent original baseline targets rather than a statement of current project status.

Budget Allocation and Cost Controls

Webster Insurance allocated $2,000,000 to GCSP, with a 4% overrun limit ($80,000) identified as a project success constraint. Reaching the $2,080,000 ceiling does not grant automatic spending authority; any cost change must go through formal organizational change control and executive approval.

Budget CategoryAllocated Amount
Project Management and Oversight$150,000
System Design and Architecture$600,000
Software Installation and Migration$150,000
Migration of Systems into the New Program$100,000
Other Project Costs and Remaining Budget$1,000,000
Total Approved Budget$2,000,000

Because $1,000,000 remains unitemized in the initial breakdown, the team should assign those funds to explicit categories such as licensing, integration labor, quality assurance testing, training, infrastructure, and contingency reserves prior to financial sign-off.

Project Objectives, Deliverables, and Scope

GCSP replaces an aging customer service database that has experienced crashes, service bottlenecks, and member dissatisfaction as Webster Insurance grows. Success depends on tying each objective to documented, measurable acceptance criteria.

Primary Business and Compliance Objectives

The new customer service platform is intended to support growth and operational efficiency through several core outcomes:

  • Increase system availability and reliability for customer service teams.

  • Reduce average call-handling time, service delays, and operating costs.

  • Provide a clear, accessible agent interface while supporting growing membership.

  • Migrate required customer and operational records accurately from the legacy database.

  • Integrate the replacement platform with relevant existing systems.

  • Satisfy applicable CMS rules and HIPAA privacy and security obligations.

  • Complete testing, staff training, technical documentation, and formal sign-off before closure.

Lifecycle Deliverables

Tangible outputs across the project lifecycle must be assigned to clear owners, verified against acceptance criteria, and approved at key milestones:

  • Initiation Deliverables: Team rosters, the project management plan, initial meeting schedules, stakeholder roles, reporting rules, and documented assumptions.

  • Design and Delivery Deliverables: Integration specifications, meeting notes, progress reports, updated schedules, system demonstrations, and architectural or migration decision logs.

  • Final Delivery and Acceptance Package: Completed program database, system integrations, integration summary, applicable CMS compliance sign-off, financial closeout records, formal customer acceptance, and lessons learned.

Any skipped numbers in the original deliverable list should be standardized into a single approved register so items are not overlooked during sign-off.

Scope Inclusions and Exclusions

Maintaining strict scope boundaries prevents unapproved expansion and protects cost and schedule baselines.

  • In Scope: Project management, system design, scheduling, software licensing and upgrades, data migration, system integration, quality assurance and user acceptance testing, deployment planning, maintenance arrangements, operational training, and a product package containing the Salesforce contract and PDF design presentation.

  • Out of Scope: Replacing unrelated systems, customer travel or lodging costs, unapproved design modifications without added funding, training on unrelated tools, and post-completion onboarding.

Execution Approach, WBS, and Schedule

GCSP uses structured planning, cross-functional coordination, and phased rollout so customer service agents can continue assisting policyholders while the new system is built and introduced.

Management and Compliance Workflow

The team starts by validating business requirements and cataloging limitations in the current database. From there, specialists build the target architecture, configure the platform, plan data migration, and define integration interfaces.

Compliance reviews should happen continuously throughout execution rather than waiting until launch. Catching regulatory or security gaps early keeps remediation practical and cost-effective. Project progress is tracked against approved milestones, budget baselines, and acceptance criteria, with Angela Guthrie coordinating department leads, resolving day-to-day conflicts, and escalating issues beyond her authority.

Phase-Level Work Breakdown Structure

WBS IDActivityOriginal StartOriginal FinishPrimary Deliverables
1.0Project InitiationJune 1, 2021June 15, 2021Team roster and project management plan
1.1System Design and ArchitectureJune 16, 2021August 30, 2021System design document and architecture plan
1.2Software Installation and MigrationSeptember 1, 2021November 30, 2021Installed software and migration report
1.3System Integration and TestingDecember 1, 2021February 28, 2022Integration report and testing results
1.4Delivery and AcceptanceMarch 1, 2022May 31, 2023Final system and compliance sign-off

Detailed Task Schedule and Sequence Check

WBS IDTask DescriptionOriginal Target Date
1.1Verify customer needs and project requirementsJune 1, 2021
1.3Confirm Salesforce as the selected softwareJune 15, 2021
1.2Create the project scheduleJuly 1, 2021
1.4Identify project stakeholdersJuly 1, 2021
2.1Develop the bid or request for proposalJuly 5, 2021
2.2Release bid or request-for-proposal documentsJuly 10, 2021
2.3Review bid documentsJuly 11, 2021
2.4Finalize the vendor contractJuly 17, 2021
3.1Develop the design responsibility matrixAugust 15, 2021
3.2Complete the new system designDecember 1, 2022
5.1Perform compliance testingDecember 5, 2022
3.3Obtain design approvalDecember 5, 2022
3.4Prepare the final program releaseJanuary 1, 2023
4.1Begin usability testingJanuary 1, 2023
4.2Finalize program deploymentMarch 1, 2023
4.3Install the system and confirm accessApril 1, 2023
5.2Provide customer trainingMay 15, 2023
5.3Obtain customer sign-off and document lessons learnedMay 31, 2023

Several target dates and task sequences in the original plan conflict or appear out of order, such as listing compliance testing on December 5, 2022, before the final program release on January 1, 2023, and placing usability testing alongside or after release milestones. Using a scheduling tool such as Microsoft Project, the project manager should reconcile dependencies, milestones, and dates before locking the schedule baseline.

Stakeholders, Roles, and Communications

Clear accountability and predictable reporting keep departments aligned across design, integration, compliance, and customer support.

Key Roles and Responsibilities

NameRolePrimary ResponsibilityProject Involvement
Steve SmithProject SponsorProvides sponsorship and approvalsAll phases
Angela GuthrieProject ManagerCoordinates scope, schedule, budget, risks, and deliveryAll phases and tasks
Ingrid SingProduct ManagerEnsures the solution meets customer needsDesign and engineering
Tracy WeaveHuman Resources ManagerAddresses staffing and HR-related mattersAll phases for HR activities
Gina WillisProcurement ManagerCoordinates procurement and accounts payable/receivable tasks as assignedAll phases
Deb KeplinProject AdministratorTracks change orders and project documentationAll phases
Danny SennIntegration ManagerCoordinates system integrationProgram integration
Joyce MillerUsability ManagerOversees usability testingProgram integration
Beatrice JonesCustomer RepresentativeServes as the customer liaisonStakeholder coordination

Stakeholder Engagement Focus

High-priority stakeholders require targeted cadence and participation:

  • Amy Johnson (Program Manager): High interest and high impact; needs regular status reports, milestone updates, and cross-departmental risk alerts.

  • Charles Davidson (Lead Developer): Medium interest and high impact; benefits from weekly development check-ins and technical feedback loops to surface integration blockers early.

  • Elizabeth Clark (Compliance Officer): High interest and medium impact; should participate in compliance reviews, requirement validation, and testing gates.

  • Michael Thompson (IT Support Lead): Medium interest and medium impact; coordinates infrastructure readiness, system access, troubleshooting, and post-launch support.

Contact details should be verified and stored in a secure project directory before distribution, and stakeholder influence levels should be updated whenever roles or decision rights shift.

PM FPX 4060 Assessment 3 Project GCSP

Communication Cadence

  • Internal Updates: Weekly project meetings and email updates covering progress, upcoming work, open issues, dependencies, and corrective actions, with more frequent technical coordination during integration and testing.

  • External Leadership Updates: Biweekly client meetings and status reports with Webster Insurance management to share progress, gather feedback, review major deliverables, and flag escalation items.

  • Change Communications: Targeted notices issued whenever changes affect requirements, integrations, budgets, or deployment dates, explaining what is changing, why it is needed, how work is affected, and what stakeholders must do next.

Risk Management, SWOT, Constraints, and Assumptions

Effective risk management for GCSP groups potential disruptions across technical, management, organizational, and resource categories using a risk breakdown structure (Hillson, 2002) and tracks them in a living risk register.

Actionable Risk Register

Risk AreaInitial AssessmentMitigation StrategyResponsible Role
Scope DefinitionInitially confirmedValidate scope and duration with stakeholdersProject team
RequirementsInitially identifiedObtain approval for system requirements and integrationsProduct manager
Estimates and AssumptionsPending verificationReview supplier estimates and regulatory requirementsProcurement manager
Technical ProcessesInitially considered adequateConfirm infrastructure and licensing requirementsProcurement manager
Legacy System CompatibilityRequires verificationTest application programming interfaces and data feedsProduct manager
External System DependenciesNone identified initiallyReassess interfaces and dependencies during designIntegration manager
Design AlignmentInitially considered adequateValidate architecture against requirements and constraintsProduct and integration managers
System PerformanceInitially expected to meet needsConduct performance and usability testingProject team
Reliability and MaintenanceRequires verificationPerform ongoing functional and operational testingProject manager and technical leads
Information SecurityCompliance expectedValidate applicable security controls throughout implementationProduct manager and compliance officer
Testing and AcceptanceTesting plannedEstablish test cases, defect thresholds, and acceptance criteriaQA and project managers
Team ResponsibilitiesRequires confirmationReview the charter and obtain role acceptanceProject manager
Operational DisruptionExpected during integrationSchedule phased deployment and prepare fallback proceduresProject manager
Departmental ConflictsUnresolved in the original planEstablish decision rights and a conflict-resolution processProject sponsor
Resource AvailabilityInitially considered adequateConfirm capacity, skills, and workload throughout the projectProject team

Entries originally marked as not applicable or undetermined should be actively reviewed rather than assumed closed. In particular, an initial note that system safety was not addressed warrants follow-up to confirm operational continuity, access controls, and safety safeguards.

SWOT Analysis

  • Strengths: Experienced project staff, executive backing, a clear business need for modernized service software, ongoing organizational growth, and a structured project management framework.

  • Weaknesses: Need to maintain live customer service during a phased cutover, higher coordination demands while old and new processes overlap, lean specialist staffing, and estimates or records requiring verification.

  • Opportunities: Faster call handling, higher system reliability, better access to customer data, standardized workflows, stronger reporting, and future service improvements.

  • Threats: Integration errors, unexpected costs, compliance gaps, schedule slips, technical skill gaps, and potential member attrition if legacy issues persist before cutover.

Constraints, Assumptions, and Success Criteria

Key constraints include the $2,000,000 budget baseline, limited single-person leadership in key roles (such as one product manager and one integration manager), busy service periods requiring phased rollout, and limited pre-deployment usability testing that must be strengthened so critical workflows are verified before launch.

Key assumptions include continued financial stability at Webster Insurance, expected performance from the selected Salesforce platform, detailed design drafts, regulatory alignment, scheduled meetings, customer sign-off, and timely financial closeout. Each assumption must be tested and verified with evidence rather than taken for granted.

Project success requires meeting agreed scope, approved requirements, accurate data migration, verified integration and usability testing, regulatory sign-off, budget discipline, and measurable post-launch operational gains, including validating the projected 18-month return on investment with actual cost and savings data.

Frequently Asked Questions

What is the main goal of Webster Insurance’s GCSP project?

The Guided Customer Service Program replaces Webster Insurance’s outdated customer service database with a scalable, compliant platform that reduces call-handling delays, supports membership growth, and meets CMS and HIPAA requirements with minimal operational disruption.

Who manages the GCSP project, and what is the approved budget?

Angela Guthrie serves as project manager alongside project sponsor Steve Smith, operating under an approved budget of $2,000,000 and an original timeline from June 1, 2021, through May 31, 2023.

Why is a phased deployment important for the GCSP rollout?

Customer service staff must continue handling member inquiries while the platform is configured, integrated, and tested, so a phased deployment limits service disruption, supports controlled testing, and allows fallback before full rollout.

What schedule and risk gaps need attention before locking execution?

The project manager should reconcile overlapping or out-of-sequence WBS dates (such as compliance testing relative to final release and usability testing), allocate the remaining $1,000,000 budget into defined categories, resolve departmental decision rights, and verify any items initially marked undetermined or unaddressed.

References

Centers for Medicare & Medicaid Services. (n.d.). Regulations and guidance. U.S. Department of Health and Human Services. https://www.cms.gov/regulations-and-guidance

Hillson, D. (2002). Extending the risk process to manage opportunities. International Journal of Project Management, 20(3), 235–240. https://doi.org/10.1016/S0263-7863(01)00074-6

U.S. Department of Health and Human Services. (n.d.). Health information privacy (HIPAA). https://www.hhs.gov/hipaa/index.html