The NearlyFree.com New Employee Orientation (NEO) training system project is currently behind schedule and over budget, with a Schedule Performance Index (SPI) of 0.60 and a Cost Performance Index (CPI) of 0.76. Based on an Earned Value of $12,373.95, a Planned Value of $20,453.95, and an Actual Cost of $16,373.95, the project is forecasted to reach a final Estimate at Completion (EAC) of approximately $29,505. This represents a projected budget overrun of $7,205, or 32.3%, above the original $22,300 budget unless management implements targeted corrective actions.
NearlyFree.com initiated the New Employee Orientation (NEO) project to build and launch an automated, web-based onboarding platform. The primary goal of this system is to streamline new hire training, improve content consistency across the organization, and reduce the administrative workload placed on human resources personnel.
Originally approved with a Budget at Completion (BAC) of $22,300 and a timeline of 92 days, the project has encountered substantial execution bottlenecks. While progress reports indicate the project is roughly 43% complete, financial data reveals that spending has outpaced actual work delivery. Conducting a formal Earned Value Analysis (EVA) allows leadership to diagnose these variances, reconcile conflicting completion metrics, and build a realistic recovery roadmap.
Earned Value Management (EVM) is an integrated project control methodology that measures project performance by combining scope, schedule, and cost baselines into a single objective framework. Unlike traditional accounting reviews that only compare planned budgets against actual cash spent, EVM evaluates expenditures directly against the monetary value of work physically completed (Project Management Institute [PMI], 2017).
By tracking these variables simultaneously, project managers can identify whether a project is truly healthy or merely masking schedule delays behind lower-than-expected spending.
To evaluate the NearlyFree.com NEO project, three foundational metrics are extracted from the project documentation. Note that legacy project records often use older terminology (BCWP, BCWS, and ACWP), which map directly to modern PMI standards:
Earned Value (EV) / Budgeted Cost of Work Performed (BCWP): The approved budget value assigned to the work actually completed by the reporting date.
Planned Value (PV) / Budgeted Cost of Work Scheduled (BCWS): The authorized budget assigned to the work scheduled to be finished by the reporting date.
Actual Cost (AC) / Actual Cost of Work Performed (ACWP): The total real-world expenditure incurred to accomplish the completed work during the reporting period.
| EVM Metric | Legacy Terminology | Reported Amount | Project Status Meaning |
|---|---|---|---|
| Earned Value (EV) | BCWP | $12,373.95 | Budgeted value of work finished to date |
| Planned Value (PV) | BCWS | $20,453.95 | Budgeted value of work scheduled to date |
| Actual Cost (AC) | ACWP | $16,373.95 | Actual money spent on completed work |
| Budget at Completion (BAC) | Original Budget | $22,300.00 | Total authorized baseline budget |
Schedule Variance measures the financial difference between the work actually performed and the work scheduled to be done by the reporting date.
A negative Schedule Variance of -$8,080.00 confirms that the NearlyFree.com project is significantly behind schedule. Because SV is expressed in dollars rather than calendar days, this figure represents the budgeted value of the work backlog. Project leadership must review the task network and critical path to translate this $8,080.00 shortfall into an exact number of delayed days.
Cost Variance measures the financial gap between the budgeted value of completed work and the actual funds spent to deliver it.
A negative Cost Variance of -$4,000.00 indicates that the project has spent $4,000.00 more than the baseline value of the work produced. While the total $22,300.00 budget has not yet been exhausted, the current burn rate is unsustainable. Without intervention, cost overruns will continue to compound through the remainder of development.
The Schedule Performance Index converts schedule variance into an efficiency ratio by dividing Earned Value by Planned Value.
An SPI of 0.60 means the project team is accomplishing only $0.60 worth of planned work for every $1.00 of work scheduled. In Earned Value Management, an SPI below 1.0 signals unfavorable schedule performance, an SPI of 1.0 indicates on-time execution, and an SPI above 1.0 reflects ahead-of-schedule progress. At 60% schedule efficiency, the team is missing major onboarding system milestones.
The Cost Performance Index measures budget efficiency by dividing Earned Value by Actual Cost.
A CPI of 0.76 indicates that NearlyFree.com is generating only $0.76 in earned work value for every $1.00 spent. Any CPI below 1.0 represents an unfavorable cost overrun. Common drivers behind a 0.76 CPI include underestimated technical complexity in web development, unbudgeted rework, inefficient developer allocation, or weak vendor cost controls.
Budget at Completion (BAC) is the original total budget of $22,300.00. Because current cost efficiency is poor, management must calculate the Estimate at Completion (EAC) to forecast the true final price tag assuming current spending trends persist.
Using the remaining budgeted work ($22,300.00 – $12,373.95 = $9,926.05) and the exact unrounded CPI (0.7557095):
(Note: Using a rounded CPI of 0.76 yields $29,434.54. Relying on unrounded figures provides a more accurate financial projection of $29,505.00.)
If current cost performance remains unchanged, the NearlyFree.com NEO project will exceed its $22,300.00 baseline by $7,205.00, representing a 32.3% total budget overrun.
| Performance Indicator | Formula | Calculated Value | Management Interpretation |
|---|---|---|---|
| Schedule Variance (SV) | EV−PV | -$8,080.00 | Behind schedule by $8,080 in planned work |
| Cost Variance (CV) | EV−AC | -$4,000.00 | Over budget by $4,000 for work delivered |
| Schedule Performance Index (SPI) | EV/PV | 0.60 (0.605) | Operating at 60% schedule efficiency |
| Cost Performance Index (CPI) | EV/AC | 0.76 (0.756) | Earning $0.76 of value per $1.00 spent |
| Remaining Work (BAC – EV) | BAC−EV | $9,926.05 | Remaining baseline value to be completed |
| Estimate at Completion (EAC) | AC+((BAC−EV)/CPI) | ~$29,505.00 | Projected final cost (32.3% over budget) |
Simply extending the 92-day deadline or approving emergency funds will not fix underlying operational flaws. To bring the automated orientation system back under control, leadership should execute a six-step turnaround plan.
The project documentation contains a critical data discrepancy: narrative reports state the project is 43% complete, yet the Earned Value of $12,373.95 equals 55.5% of the $22,300.00 budget. Before approving a revised baseline, the project manager must audit how progress is measured. Physical task completion rules and budget-weighted EV calculations must follow the exact same standard so leadership is not making funding decisions based on flawed reporting.
The project manager should conduct a root-cause analysis of the critical path to identify which deliverables caused the -$8,080.00 schedule variance. Where technical dependencies allow, non-sequential web development tasks should be fast-tracked in parallel. However, management must avoid adding excessive overtime or extra staff without evaluating productivity diminishing returns, which could further degrade the CPI.
Management should audit all remaining work packages ($9,926.05 in baseline value) to separate unavoidable technical costs from preventable rework. If the $29,505.00 forecast holds true, the project manager must submit a formal change request outlining the $7,205.00 funding gap, expected return on investment from onboarding automation, and the operational impact of delaying launch.
Scope creep is a primary driver of cost overruns in internal software builds. All non-essential features, custom animations, or secondary reporting modules should be deferred to a Phase 2 release. The immediate priority must remain launching a stable, minimum viable web-based orientation system that fulfills core HR training requirements.
Monthly reviews are too slow for a project operating at a 0.60 SPI. NearlyFree.com should transition to weekly EVM reporting that tracks EV, PV, AC, CPI, and SPI at the work-package level. Management should establish clear variance thresholds (for example, triggering an immediate review if weekly CPI drops below 0.85) to catch bottlenecks early.
The NearlyFree.com case demonstrates that baseline budgets only protect organizations when paired with continuous variance monitoring. Establishing standardized progress-tracking definitions at kickoff and reviewing Earned Value metrics biweekly or weekly prevents minor delays from snowballing into 30%+ budget overruns.
Earned Value Analysis (EVA) is a quantitative project tracking method that compares the budgeted value of completed work (Earned Value) against the budgeted value of scheduled work (Planned Value) and actual money spent (Actual Cost). It gives project managers an objective view of schedule delays, cost efficiency, and forecasted final costs.
No. The NearlyFree.com project has a Schedule Variance of -$8,080.00 and a Schedule Performance Index (SPI) of 0.60. This indicates that the team has completed only 60% of the work scheduled by the reporting date.
If current spending efficiency continues, the project is forecasted to finish at approximately $29,505.00 against its original $22,300.00 budget. This represents a projected cost overrun of $7,205.00, or 32.3%.
A CPI of 0.76 means the project is earning $0.76 worth of budgeted work for every $1.00 actually spent. Because the ratio is below 1.0, the project is experiencing unfavorable cost performance and losing money relative to its baseline plan.
An SPI of 0.60 means the project is progressing at 60% of its planned rate, completing $0.60 of work for every $1.00 of work scheduled. While it confirms a severe delay, an additional critical path schedule review is needed to determine the exact number of calendar days behind schedule.
When future work is expected to proceed at the same cost efficiency experienced so far, Estimate at Completion is calculated using the formula EAC=AC+((BAC−EV)/CPI)EAC = AC + ((BAC – EV) / CPI)EAC=AC+((BAC−EV)/CPI). Plugging in NearlyFree.com’s exact figures ($16,373.95 + ($9,926.05 / 0.7557095)) yields an estimated final cost of approximately $29,505.00.
The report states the project is 43% complete, yet the Earned Value of $12,373.95 equals 55.5% of the $22,300.00 total budget. This happens when physical task completion estimates and financial Earned Value rules are calculated using different criteria, requiring a data reconciliation audit before approving new budgets.
Cullen, S. (2016, August 2). Earned value analysis. Whole Building Design Guide. https://www.wbdg.org/resources/earned-value-analysis
Haughey, D. (2020, July 26). What is earned value? Project Smart. https://www.projectsmart.co.uk/what-is-earned-value.php
Peng, B. (2018, April 10). The earned value method. Project Engineer. https://www.projectengineer.net/the-earned-value-method/
Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK® guide) (6th ed.). Project Management Institute. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Usmani, F. (2020, August 18). Planned value (PV), earned value (EV) and actual cost (AC) in project cost management. PM Study Circle. https://pmstudycircle.com/2012/05/planned-value-pv-earned-valueev-actual-cost-ac-analysis-in-project-cost-management-2/